Render of Brigalow Peaking Power Plant

Brigalow Peaking Power Plant 

Fast Facts

  • Gas peaker, 400 MW capacity
  • 12 x GE Vernova aeroderivative turbines 
  • Fast start – 5 minutes from cold to full output
  • Located on the traditional lands of the Barunggam people
  • Under construction. Operational in 2029

Project overview

The Brigalow Peaking Power Plant is a 400 MW gas peaking plant that is being constructed next to Kogan Creek Power Station.

Featuring an open cycle design, the power plant will have fast-start capability and operate in high demand periods to underpin power system reliability. Once operational, the power plant will have the ability to start up and deliver full output within five minutes, delivering reliable energy supply to more than 150,000 Queensland homes.

Brigalow Peaking Power Plant
Image: The Brigalow Peaking Power Plant will have 12 GE Vernova aeroderivative turbines.

Who's involved

CS Energy is developing the project in a partnership with APA, an ASX listed energy infrastructure business.

APA will own 80 per cent of the project and is leading delivery under a construction management agreement. Once complete, CS Energy will operate and maintain the power plant and retain a 20 per cent ownership interest.

APA’s share of the plant will be contracted to CS Energy under a 25-year hedge offtake agreement, meaning CS Energy will have 100 per cent of the plant’s offtake.

Gas producer Senex will supply natural gas for the power station from its Atlas development in Queensland's Surat Basin. The gas will be transported to the power plant via a 23-kilometre APA pipeline, which will connect to the existing Roma Brisbane Pipeline. 

Brigalow Peaking Power Plant
Image: A render of the Brigalow Peaking Power Plant (foreground) with the existing Kogan Creek Power Station in the background.

current status

The Brigalow Peaking Power Plant is targeted for completion in early 2029. Early project works are now complete, GE Vernova is delivering the gas turbines and Balance of Plant contractor Monadelphous is delivering the main construction works.

Brigalow Peaking Power Plant
Image: The Brigalow construction site in November 2026.

Community

CS Energy will keep our immediate neighbours and the Chinchilla community informed as this project progresses. For more information, please refer below.

For more information, please contact us on 1800 318 500 or send us an email.

About the Brigalow Peaking Power Plant

The Brigalow Peaking Power Plant will consist of a compact power station footprint (350m x 150m). It will be built on previously cleared land within the existing Kogan Creek Power Station site boundaries. 


 

With its fast-start ability, the Brigalow Peaking Power station will provide on-demand electricity for high demand periods and support variable solar and wind energy.

 

Natural gas will be transported to the Brigalow Peaking Power Plant via a proposed 23-kilometre pipeline that would connect to APA Group's existing Roma Brisbane Pipeline.

 

 

The open cycle design of the technology chosen provides the ability for multiple start/stop cycles per day and the ability to ramp up to full power output within five minutes, meaning the plant can be on the grid quickly and stay on for long durations. This is important in helping to address the variability of renewable energy generation and providing firm capacity to the grid in addition to the role of batteries and pumped hydro. The turbines will also be capable of operating in ‘synchronous condenser’ mode, which enables them to provide system strength and grid support during times of high renewables output without burning gas. 

 

 

More information

The project will be capable of producing up to 400 MW of power. This is enough capacity to power more than 150,000 average Queensland homes during peak periods. 

 

 

Extensive studies have been completed to inform the project design. Development approval and an Environmental Authority have been obtained. The project remains subject to CS Energy and other relevant government approvals.

media releases