Kogan turbine hall

Outages

CS Energy operates and maintains our assets to ensure they are available to provide affordable, reliable and sustainable electricity for Queenslanders.

We carry out regular planned outages to perform statutory maintenance and overhauls of our generating units.

Unplanned outages can occur from time to time, and when this occurs, our priority is carrying out the repairs safely, while also working to minimise plant downtime wherever possible.

power plant status

The table below shows the current operational status of the power stations that we own and operate. Refer further below for outage dates and details.

Unit Status
Callide B1 Online
Callide B2 Online
Callide C3 Online
Callide C4 Online
Kogan Creek Planned outage
Chinchilla Battery Online
Greenbank Battery Online
Last updated on 28 June, 7.51am

Outage info

Details of current outages

  • Kogan Creek Power Station planned outage (28 June - 4 July 2025) - this outage is required to carry out repairs to a relay connected to Powerlink’s transmission line protection system. 

Recent outages

  • Callide Unit C3 went offline on 4 April after a major operational safety event. The unit was returned to service shortly before 3am on Sunday 1 June.
  • Callide Unit B2 went offline on 16 May for a planned outage for precipitator repairs, low pressure turbine blade inspections, and other maintenance . The unit returned to service at 7.15am on Friday 13 June.
  • Callide Unit B1 went offline from 02:20am on 27 May - the unit tripped when site was performing a routine changeover on flame detector cooling fan. The unit was returned to service at 04.20am the same day.

Future outages

The table below shows future planned outages for the current calendar year.

Asset Outage type Start date End date
Kogan Creek  Planned outage - replacement of a relay connected to transmission line protection system 28 June 2025  4 July 2025
Callide Unit C3  Planned - major overhaul 15 August 2025  10 November 2025 
Callide Unit B1  Planned - precipitator maintenance 29 August 2025 19 September 2025
Callide Unit B2  Planned - precipitator maintenance 26 September 2025  17 October 2025
Kogan Creek  Planned - pre-summer readiness maintenance 15 November 2025  6 December 2025 

 

About this page

 

The content on this page is consistent with information available via the Australian Energy Market Operator (AEMO).

Under the National Electricity Rules (Clause 3.7.2), CS Energy must keep AEMO informed of our current intentions and best estimates for the availability of our generating units. 

Page last updated: Saturday, 28 June 2025 7:56:51 AM