Plant Outages

FORCED GENERATION OUTAGES File Updated: 11/08/2008 08:00AM

Station Unit

Mws Offline

Start Date

Finish Date

Outage Description

       

 



PLANNED GENERATION OUTAGES File Updated: 11/08/2008 08:00AM

Station Unit

Mws Offline

Start Date

Finish Date

Outage Description

 
SWANBANK E 385 22-August-2008 25-August-2008

'A' Inspection

SWANBANK B UNITS3&4  240 30-August-2008 7-September-2008

Station maintenance

SWANBANK B UNITS1&2  240 13-September-2008 22-September-2008

Station maintenance

KOGAN CREEK 750 17-October-2008 07-November-2008

8000hr Inspection

SWANBANK B3 120 13-February-2009 22-March-2009

Overhaul

CALLIDE B1 350 03-April-2009 13-May-2009

Overhaul

CALLIDE B2 350 03-April-2009 12-June-2009

Overhaul

SWANBANK E 385 20-June-2009 26-July-2009

'C' Inspection

Collinsville 1 30 15-August-2009 22-August-2009

 

Collinsville 2 30 15-August-2009 22-August-2009

 

Collinsville 3 31 15-August-2009 22-August-2009

 

Collinsville 4 31 15-August-2009 22-August-2009

 

Collinsville 5 66 15-August-2009 22-August-2009

 

SWANBANK B4 120 16-October-2009 22-November-2009

Overhaul

SWANBANK E 370 25-November-2009 27-November-2009

'A' Inspection

SWANBANK E 370 03-August-2010 07-August-2010

'B' Inspection

KOGAN CREEK 750 08-August-2010 25-August-2010

Overhaul

CALLIDE B1 350 01-September-2010 08-November-2010

Overhaul

Note This table for CS Energy's NEM connected plant only.  This information is correct at time of issuing. CS Energy accepts no liability for or arising from the changes that are made and not immediately updated